Local Erosion of the Channel After Reinforcement of the Millrace of the Votkinsk Hydroelectric Power Plant
- Авторлар: Veksler A.B.1, Fisenko V.F.2
-
Мекемелер:
- JSC “VNIIG im. B. E. Vedeneeva”
- Votkinsk HPP, branch of JSC RusHydro
- Шығарылым: Том 51, № 1 (2017)
- Беттер: 14-19
- Бөлім: Article
- URL: https://journal-vniispk.ru/1570-145X/article/view/245558
- DOI: https://doi.org/10.1007/s10749-017-0775-2
- ID: 245558
Дәйексөз келтіру
Аннотация
Changes during operation in the state of the segment where concrete reinforcement of the water channels of the Votkinsk hydroelectric plant join the Kama River are examined. The reasons for erosion during the 1990’s, including lowering of the water levels in the lower millrace, are examined. It is noted that after reinforcement of the hopper during 1998 – 2000, the state of this segment remains satisfactory and does not threaten the safety of the equipment.
Негізгі сөздер
Авторлар туралы
A. Veksler
JSC “VNIIG im. B. E. Vedeneeva”
Хат алмасуға жауапты Автор.
Email: VekslerAB@vniig.ru
Ресей, St. Petersburg
V. Fisenko
Votkinsk HPP, branch of JSC RusHydro
Email: VekslerAB@vniig.ru
Ресей, Votkinsk
Қосымша файлдар